Superior Concrete Home
about Superior Concrete see our work about the laser screed about tiltwalls
about stamped concrete about cast-in-place walls about foundations contact Superior Concrete
 

 

Here is a list of projects that Superior Concrete has been involved in. Click on the pictures to get more details.


JOB: BERRY PLASTICS DISTRIBUTION CENTER
CUSTOMER: Berry Plastics, Inc.
CONTRACTOR: The Kunkel Group
PROJ MGR: John Wood 812-305-5720
  Job consisted of 600,000 SF Distribution Center, with 142,000 SF of tilt wall panels.  The panels were designed by our own alliance contractor, CONSTEEL ALLIANCE.  The floor is a 7” fiber reinforced concrete floor over 4” of stone.  All foundations are supported by 36” caissons drilled into shale stone below.  The first floor pour was on May 21, 2007, and the last tilt panel was stood on August 2, 2007.  Over 17,000 CYS of concrete placed in 11 weeks. Bob Foley, the president of CONSTEEL say’s it’s the best overall concrete tilt wall job he has seen in forty years. There is also approximately 112,000 SF of exterior paving, and 3,000 Lf of concrete ditch bottoms.

JOB: COLUMBIA SPORTSWEAR WAREHOUSE
CUSTOMER: Columbia Sportswear
CONTRACTOR: Perlo McCormack Pacific
PROJ MGR: Marlin Steenblock (503) 701-8151
  Project consisted of 457,000 s.f. of interior floors, 55,000 s.f. of mezzanine floors, 211,000 s.f. of tilt wall panel, 3,800 l.f. of foundations, 125,000 s.f. of exterior concrete, a total of 22,000 cubic yards of concrete.  Job was started November of 2003, and the building was occupied by June of 2004.

JOB: FIA 1500 & 2500 PRESS PIT BUILDING
CUSTOMER: Futaba of Indiana
CONTRACTOR: Takenaka (USA) Corporation
PROJ MGR: Yasushi Arai (630) 250-3400
  Job consisted of a 145,000 s.f. manufacturing warehouse complete with foundations, perimeter walls, and dock pits.  Also included were three deep pits that averaged 16 feet deep and over 300 l.f. of cast-in-place conveyor tunnel to support press machines for the auto industry. A sheet piling and dewatering system was installed to dewater the pits during construction as the project was constructed in sandy soils with a water table at 7 feet below finished floor level.  One year after completion of the original press building, Takenaka contacted Superior Concrete to install an additional 2,500 ton press pit.  This pit was placed between two working presses.  Again a sheet pile and dewatering system was installed to allow excavation to 22 feet below the existing floor.  The new pit was tied into the existing tunnels seamlessly without disturbing FIA’s production.

JOB: WAREHOUSE / OFFICE FACILITY
CUSTOMER: Panatonni / Bristol Myers
AGENT: DPR Construction
CONTACT: Guy Sanders - Project Manager (602) 469-0414
  Project consisted of 600,000 s.f. of 6" slab on grade over 4" - #53 stone Warehouse floor, with 12,000 s.f. of office flooring and foundations with floors specified to maintain FF 45 or above. . All perimeter foundations, spread footings and 84 truck docks were also included. Also, Superior Concrete performed the place and finish of the approximately 200,000 s.f. of tilt wall construction. Total project concrete is over 20,000 cubic yards. Foundations were started July 6, 1999. Slabs were completed along with all foundations by the end of August 1999. Bristol Myers took occupancy by November 15, 1999

JOB: FREEZER BUILDING AND OFFICES
CUSTOMER: Roundy's
AGENT: Tippmann Construction
CONTACT: Dale Budzon (219) 490-3000
  Job consisted of perimeter foundations, grade beams, 138,000 s.f. of finish floors with F-numbers above 50 and 250,000 s.f. concrete parking lot. A total of 8,000 cubic yards of concrete was placed. Also included under our scope was the structural steel, roofing, electrical, plumbing, HVAC and finishes for the offices. Superior performed as General Contractor. Size of our scope was $2.5 million.

JOB: DISTRIBUTION WAREHOUSE
CUSTOMER: Shoe Carnival
CONTRACTOR: Woodward Development & Construction
PROJ MGR: Steve Kahre  (812) 474-1900
  Project consisted of a 410,000 s.f. warehouse facility including all perimeter and interior foundations and slabs.  Included was an 800 l.f. dock retaining wall with 60 dock leveler pits, 390,000 s.f. of exterior paving with over 1,400 l.f. of integral 12 inch tall roll curb in lieu of truck parking bumpers.

JOB: WAREHOUSE
CUSTOMER: Vuteq
AGENT: Takenaka (Usa) Corporation
CONTACT: Nick Scheessele (317) 670-8009


Job consisted of 180,000 SF Warehouse complete with foundations, perimeter walls and dock pits. Also included were 46,000 SF concrete paving and concrete curbs and sidewalks. Job started June 21, 2001 and was completed October 20, 2001.


JOB: WAREHOUSE
CUSTOMER: Grahmam Packaging
AGENT: Woodward Commercial Realty
CONTACT: Evan Beck (812) 474-1900
  142,000 SF Warehouse facility including all perimeter and interior foundations. Included is 350 L.F. of dock retaining wall, 93,000 SF of exterior paving, 2,500 L.F. curb/gutter, sidewalks, aprons.

JOB: MULTI-FLOOR HOSPITAL ADDITION
CUSTOMER: Lourdes Hospital
AGENT: KDA Holdings, Inc.
CONTACT: Ron Henley, Director of Facilities (270) 444-2182
  Job consisted of heavily reinforced grade beams resting on drilled caissons, a 25,000 S.F. basement and 5 floors of lightweight concrete on deck at 25,000 S.F. per floor, with the job totaling 150,000 S.F.

JOB: UTILITY BUILDING
CUSTOMER: Toyota Motor Manufacturing Indiana, Inc.
AGENT: Grey/Ellis Don Construction Co.
CONTACT: Ken Kirby (812) 385-3966
  Project consisted of pipe rack foundations placed over angle cast piles, a 10,000 SF Utility Building expansion and a 6,500 SF Cooling Tower Basin with some 150 formed concrete support piers.

JOB: ATLAS VAN LINES - NEW OFFICE ADDITION
CUSTOMER: Atlas Van Lines
AGENT: Wink Construction, General Contractor
CONTACT:   Don Johnson - Project Manager (812) 476-6216
 

Project consisted of 4,300 s.f. basement with 14 foot tall poured walls, 30,000 s.f. main floor, and 30,000 s.f. second floor. Second floor was heavily reinforced with light weight concrete. Thirteen thousand s.f. of sidewalk, 6,800 l.f. of poured curb, and a 75 foot long dock area were also included. Some 153,000 lbs. of rebar was installed on this project.

 
 

Top of Page

Home

Company Profile
Contact US
Portfolio

Laser Screed
Tiltwall
Cast-In-Place
Foundations
Stamped Concret

 
Copyright © 2007 Superior Concrete Constructors Inc.