Here is a list of some of the more significant projects that Superior Concrete has been involved. Click on the pictures to obtain more details.
|
| JOB: |
Carhartt Distribution Facility |
|
| CUSTOMER: |
Carhartt, Inc. |
| CONTRACTOR: |
H & M Construction Co., Inc. |
| PROJ MGR: |
Chad Howell (731) 660-3097 |
| |
Job consisted of 250,000 s.f. building, all inclusive of foundations, formed grade beams, and rock excavation. This project included 148,000 s.f. of 6" FF 50/FL 35 floors and 110,000 s.f. of FMIN 74 Super Flat Floors. Superior Concrete achieved FF numbers above 100 on this project. Also included was a 7,500 s.f. canteen area that received a diamond polished floor. |
|
| JOB: |
Mt. Vernon IN - Ethanol Plant |
|
| CUSTOMER: |
Aventine Renewable Energy |
| CONTRACTOR: |
Kiewit Energy Co |
| PROJ MGR: |
Peter Kruse (312) 446-7442 |
| |
Job consisted of heavily reinforced 3' thick foundations to support round tanks, elevated structures, and miscellaneous building foundations. The round tanks were unique in that they had sloped perimeter walls, and tolerances were very tight. |
|
| JOB: |
Berry Plastics Distribution Center |
 |
| CUSTOMER: |
Berry Plastics, Inc. |
| CONTRACTOR: |
The Kunkel Group |
| PROJ MGR: |
John Wood (812) 305-5720 |
| |
Job consisted of 600,000 s.f. Distribution Center, with 142,000 s.f. of tilt wall panels. The panels were designed by our own alliance contractor, CONSTEEL alliance. The floor is a 7” fiber reinforced concrete floor over 4” of stone. All foundations are supported by 36” caissons drilled into shale stone below. The first floor pour was on May 21, 2007, and the last tilt panel was stood on August 2, 2007. Over 17,000 cubic yards of concrete were placed in 11 weeks. Bob Foley, the president of CONSTEEL says it is the best overall concrete tilt wall job he has seen in forty years. There is also approximately 112,000 s.f. of exterior paving, and 3,000 l.f. of concrete ditch bottoms. |
|
| JOB: |
Columbia Sportswear Warehouse |
 |
| CUSTOMER: |
Columbia Sportswear |
| CONTRACTOR: |
Perlo McCormack Pacific |
| PROJ MGR: |
Marlin Steenblock (503) 701-8151 |
| |
Project consisted of 457,000 s.f. of interior floors, 55,000 s.f. of mezzanine floors, 211,000 s.f.
of tilt wall panel, 3,800 l.f. of foundations, 125,000 s.f. of exterior concrete, a total of 22,000 cubic yards of concrete. Job was started November 2003, and the building was occupied by June 2004. |
|
| JOB: |
FIA 1500 & 2500 Press Pit Building |
 |
| CUSTOMER: |
Futaba of Indiana |
| CONTRACTOR: |
Takenaka (USA) Corporation |
| PROJ MGR: |
Yasushi Arai (630) 250-3400 |
| |
Job consisted of a 145,000 s.f. manufacturing warehouse complete with foundations, perimeter walls, and dock pits. Also included were three deep pits that averaged 16 feet deep and over 300 l.f. of cast-in-place conveyor tunnel to support press machines for the auto industry. A sheet piling and dewatering system was installed to dewater the pits during construction as the project was constructed in sandy soils with a water table at 7 feet below finished floor level. One year after completion of the original press building, Takenaka contacted Superior Concrete to install an additional 2,500 ton press pit. This pit was placed between two working presses. Again a sheet pile and dewatering system was installed to allow excavation to 22 feet below the existing floor. The new pit was tied into the existing tunnels seamlessly without disturbing FIA’s production. |
|
| JOB: |
Warehouse / Office Facility |
 |
| CUSTOMER: |
Panatonni / Bristol Myers |
| AGENT: |
DPR Construction |
| CONTACT: |
Guy Sanders - Project Manager (602) 469-0414 |
| |
Project consisted of 600,000 s.f. of 6" slab on grade over 4" - #53 stone Warehouse floor, with 12,000 s.f. of office flooring and foundations with floors specified to maintain FF 45 or above. . All perimeter foundations, spread footings and 84 truck docks were also included. Also, Superior Concrete performed the place and finish of the approximately 200,000 s.f. of tilt wall construction. Total project concrete is over 20,000 cubic yards. Foundations were started July 6, 1999. Slabs were completed along with all foundations by the end of August 1999. Bristol Myers took occupancy by November 15, 1999 |
|
| JOB: |
Freezer Building and Offices |
 |
| CUSTOMER: |
Roundy's |
| AGENT: |
Tippmann Construction |
| CONTACT: |
Dale Budzon (219) 490-3000 |
| |
Job consisted
of perimeter foundations, grade beams, 138,000 s.f. of finish floors
with F-numbers above 50 and 250,000 s.f. concrete parking lot. A
total of 8,000 cubic yards of concrete was placed. Also included
under our scope was the structural steel, roofing, electrical, plumbing,
HVAC and finishes for the offices. Superior performed as General
Contractor. Size of our scope was $2.5 million. |
|
| JOB: |
Distribution Warehouse |
 |
| CUSTOMER: |
Shoe Carnival |
| CONTRACTOR: |
Woodward Development & Construction |
| PROJ MGR: |
Steve Kahre (812) 474-1900 |
| |
Project consisted of a 410,000 s.f. warehouse facility including all perimeter and interior foundations and slabs. Included was an 800 l.f. dock retaining wall with 60 dock leveler pits, 390,000 s.f. of exterior paving with over 1,400 l.f. of integral 12 inch tall roll curb in lieu of truck parking bumpers. |
|
| JOB: |
Warehouse |
 |
| CUSTOMER: |
Vuteq |
| AGENT: |
Takenaka (Usa) Corporation |
| CONTACT: |
Nick Scheessele (317) 670-8009 |
|
Job consisted of 180,000 SF Warehouse complete with
foundations, perimeter walls and dock pits. Also included were 46,000
SF concrete paving and concrete curbs and sidewalks. Job started
June 21, 2001 and was completed October 20, 2001. |
|
| JOB: |
Warehouse |
 |
| CUSTOMER: |
Graham Packaging |
| AGENT: |
Woodward Commercial Realty |
| CONTACT: |
Evan Beck (812) 474-1900 |
| |
142,000 SF Warehouse facility including all perimeter
and interior foundations. Included is 350 L.F. of dock retaining
wall, 93,000 SF of exterior paving, 2,500 L.F. curb/gutter, sidewalks,
aprons. |
|
| JOB: |
Multi-Floor Hospital Addition |
 |
| CUSTOMER: |
Lourdes Hospital |
| AGENT: |
KDA Holdings, Inc. |
| CONTACT: |
Ron Henley, Director of Facilities (270) 444-2182 |
| |
Job consisted of heavily reinforced grade beams resting on drilled caissons, a 25,000 S.F. basement and 5 floors of lightweight concrete on deck at 25,000 S.F. per floor, with the job totaling 150,000 S.F. |
|
| JOB: |
Utility Building |
 |
| CUSTOMER: |
Toyota Motor Manufacturing Indiana, Inc. |
| AGENT: |
Grey/Ellis Don Construction Co. |
| CONTACT: |
Ken Kirby (812) 385-3966 |
| |
Project consisted of pipe rack foundations placed
over angle cast piles, a 10,000 SF Utility Building expansion and
a 6,500 SF Cooling Tower Basin with some 150 formed concrete support
piers. |
|
| JOB: |
Atlas Van Lines- New Office Addition |
 |
| CUSTOMER: |
Atlas Van Lines |
| AGENT: |
Wink Construction, General Contractor |
| CONTACT: |
Don Johnson - Project Manager (812) 476-6216 |
| |
Project consisted
of 4,300 s.f. basement with 14 foot tall poured walls, 30,000 s.f.
main floor, and 30,000 s.f. second floor. Second floor was heavily
reinforced with light weight concrete. Thirteen thousand s.f. of
sidewalk, 6,800 l.f. of poured curb, and a 75 foot long dock area
were also included. Some 153,000 lbs. of rebar was installed on
this project. |